How to set out stage payments for an extension

A good payment schedule keeps your cash flow healthy and the homeowner comfortable. Tie each payment to visible progress, keep the deposit modest and leave a real balance for completion.

Four principles

  1. Pay for progress the homeowner can see. "Foundations in", "roof on, watertight", "plastered". Not "week 3".
  2. Keep the deposit modest. Enough to secure the start date and early materials. A large sum before any work starts is what makes homeowners nervous, and many consumer guides warn them about it.
  3. Keep stages roughly in line with your costs. So you're never funding the job out of your own pocket for long.
  4. Leave a real balance for completion. It gives both sides a reason to get the snags done and signed off.

Worked examples: a £45,000 single-storey extension

Simple, four stages

Stage%NetWith VAT
Deposit10%£4,500£5,400
Foundations25%£11,250£13,500
Roof on, watertight35%£15,750£18,900
Balance on completion30%£13,500£16,200
Total100%£45,000£54,000

More stages, smaller payments

Stage%Net
Deposit10%£4,500
Foundations and slab20%£9,000
Walls up to plate20%£9,000
Roof on, watertight20%£9,000
First fix and plastering15%£6,750
Completion15%£6,750

More stages means smaller, more frequent invoices: better for your cash flow, and easier for most homeowners to budget for. Build your own in the stage payment calculator.

VAT

If you're VAT-registered, each stage invoice carries VAT on that stage. Be clear in the quote whether the price includes VAT. Homeowners compare quotes on the bottom line, and a net figure next to a competitor's gross figure causes confusion later.

Where variations fit

Don't rewrite the percentages when the job changes. Agree each change in writing with its own price, then add approved changes to the next stage invoice. The original schedule stays intact and the final account is simply the contract price plus or minus the approved variations. See how to handle variations.

Put it in writing

The schedule belongs in the quote and the contract, so it's agreed with the price. Standard forms exist for domestic work, such as the JCT contracts for home owners and the FMB's plain-English contract, or your own terms checked by a solicitor.

Worth knowing: if the contract is signed in the homeowner's home, the Consumer Contracts Regulations usually give them 14 days to cancel. If they want you to start within that period, get their express request in writing.

When a payment is late

Chase early, politely and in writing: a short reminder a few days after the due date, another a week later, then a call. Your contract should say what happens if a stage isn't paid, for example that you can pause work after notice. Never let a missed stage roll silently into the next one.

In Pegline, the schedule from the accepted quote becomes the job's invoices: one tap per stage, approved changes added automatically, and polite reminders after 3, 7 and 14 days. See stage payments.

Questions

What percentage deposit should a builder take for an extension?

There's no fixed rule. Many builders keep the deposit modest, often 10% to 15%, and move the rest into visible stages. Very large deposits tend to worry homeowners.

How many stage payments should an extension have?

Four to six is common: deposit, foundations, structure, roof on, finishes and completion.

Should the balance be paid before snagging?

Leaving a meaningful balance until completion and sign-off of snags is fairer and keeps both sides motivated to finish.