Four principles
- Pay for progress the homeowner can see. "Foundations in", "roof on, watertight", "plastered". Not "week 3".
- Keep the deposit modest. Enough to secure the start date and early materials. A large sum before any work starts is what makes homeowners nervous, and many consumer guides warn them about it.
- Keep stages roughly in line with your costs. So you're never funding the job out of your own pocket for long.
- Leave a real balance for completion. It gives both sides a reason to get the snags done and signed off.
Worked examples: a £45,000 single-storey extension
Simple, four stages
| Stage | % | Net | With VAT |
|---|---|---|---|
| Deposit | 10% | £4,500 | £5,400 |
| Foundations | 25% | £11,250 | £13,500 |
| Roof on, watertight | 35% | £15,750 | £18,900 |
| Balance on completion | 30% | £13,500 | £16,200 |
| Total | 100% | £45,000 | £54,000 |
More stages, smaller payments
| Stage | % | Net |
|---|---|---|
| Deposit | 10% | £4,500 |
| Foundations and slab | 20% | £9,000 |
| Walls up to plate | 20% | £9,000 |
| Roof on, watertight | 20% | £9,000 |
| First fix and plastering | 15% | £6,750 |
| Completion | 15% | £6,750 |
More stages means smaller, more frequent invoices: better for your cash flow, and easier for most homeowners to budget for. Build your own in the stage payment calculator.
VAT
If you're VAT-registered, each stage invoice carries VAT on that stage. Be clear in the quote whether the price includes VAT. Homeowners compare quotes on the bottom line, and a net figure next to a competitor's gross figure causes confusion later.
Where variations fit
Don't rewrite the percentages when the job changes. Agree each change in writing with its own price, then add approved changes to the next stage invoice. The original schedule stays intact and the final account is simply the contract price plus or minus the approved variations. See how to handle variations.
Put it in writing
The schedule belongs in the quote and the contract, so it's agreed with the price. Standard forms exist for domestic work, such as the JCT contracts for home owners and the FMB's plain-English contract, or your own terms checked by a solicitor.
Worth knowing: if the contract is signed in the homeowner's home, the Consumer Contracts Regulations usually give them 14 days to cancel. If they want you to start within that period, get their express request in writing.
When a payment is late
Chase early, politely and in writing: a short reminder a few days after the due date, another a week later, then a call. Your contract should say what happens if a stage isn't paid, for example that you can pause work after notice. Never let a missed stage roll silently into the next one.
In Pegline, the schedule from the accepted quote becomes the job's invoices: one tap per stage, approved changes added automatically, and polite reminders after 3, 7 and 14 days. See stage payments.
Questions
What percentage deposit should a builder take for an extension?
There's no fixed rule. Many builders keep the deposit modest, often 10% to 15%, and move the rest into visible stages. Very large deposits tend to worry homeowners.
How many stage payments should an extension have?
Four to six is common: deposit, foundations, structure, roof on, finishes and completion.
Should the balance be paid before snagging?
Leaving a meaningful balance until completion and sign-off of snags is fairer and keeps both sides motivated to finish.