Guide for builders

What happens after planning permission is granted?

Planning permission is the start, not the finish. Here's what has to happen before the first spade goes in, and where the builder fits in, so you can talk the homeowner through it.

The decision notice

When permission is granted, the council issues a decision notice. Read all of it, not just the first line. It lists the approved drawings (build what's on them), the time limit, and the conditions. For most permissions the time limit is three years to start work.

Conditions

Conditions are the rules attached to the permission: matching materials, obscure glazing on a side window, no windows in a flank wall, tree protection. Some are pre-commencement conditions, which have to be discharged (approved by the council) before work starts. Starting without discharging them can put the permission at risk, so check them before you agree a start date.

Building regulations: a separate approval

Planning permission is about what the building looks like and its effect on neighbours. Building regulations are about how it's built: structure, fire safety, insulation, drainage, ventilation. Almost every extension needs building regulations approval, from either the council's building control or a registered building control approver. Full plans approval (drawings checked before work) or a building notice (for simpler work) are the two usual routes. At the end, building control issues a completion certificate. Make sure it goes in the handover pack.

Party walls

If the work involves a shared wall, building on the boundary, or digging foundations close to a neighbour's, the Party Wall etc. Act 1996 probably applies. The homeowner must serve notice on the neighbours, generally two months before work on a party wall and one month before excavation work, and the neighbour can agree or appoint a surveyor. It's the homeowner's duty, but it affects your start date, so raise it early.

CDM and dutyholders

The Construction (Design and Management) Regulations 2015 apply to domestic projects too. For a domestic client, most client duties pass to the contractor (or the principal contractor where there's more than one contractor), so on a typical extension that's usually you. Since October 2023, the Building Regulations also set out dutyholder roles for building work, including a principal designer and principal contractor where more than one contractor is involved. Know which roles you're taking on before you sign.

Where the builder comes in

This is the window when most homeowners choose their builder: permission in hand, drawings done, conditions and building regulations to sort, start date to agree. A builder who gets in touch now, explains the steps clearly and gives a quote with the payment stages set out looks like the safe pair of hands they're hoping for.

That's why Pegline shows you each application the week it's decided, and why the letter it prepares goes out that same week. See how Pegline finds the work.

Questions

How long does planning permission last?

Usually three years to start work, unless the decision notice says otherwise.

Is planning permission the same as building regulations approval?

No. They are separate approvals. Most extensions need both.

Who serves party wall notices: the builder or the homeowner?

The building owner (the homeowner) is responsible, though builders often help them get it done in time.

One builder per district. Is yours still free?

Tell Pegline your district and the work you do. You'll get a straight answer, and a look at the jobs in your patch this week.